APPROVED |
2024/04/06 10:00 |
2024/06/24 10:00 |
Maintenance |
|
APPROVED |
2024/04/21 12:00 |
2024/04/26 17:00 |
Urgency outage for STR072 and PST to do PT and lighting arrestors testing. Asking to isolate on Friday night (whatever time works best for ECC/PSO). |
|
APPROVED |
2024/04/21 12:00 |
2024/04/26 17:00 |
Urgency outage for STR072 and PST to do PT and lighting arrestors testing. Asking to isolate on Friday night (whatever time works best for ECC/PSO). *Spare** |
|
APPROVED |
2024/04/21 12:00 |
2024/04/26 17:00 |
Urgency outage for STR072 and PST to do PT and lighting arrestors testing. Asking to isolate on Friday night (whatever time works best for ECC/PSO). *Spare** |
|
APPROVED |
2024/04/21 12:00 |
2024/04/26 17:00 |
Urgency outage for STR072 and PST to do PT and lighting arrestors testing. |
|
APPROVED |
2024/04/22 08:30 |
2024/05/10 16:00 |
T3 outage for maintenance and repair for 3 weeks. * HVPST
Returning R1 to service. |
|
APPROVED |
2024/04/22 08:30 |
2024/05/10 16:00 |
T3 outage for maintenance and repair for 3 weeks. * Relay
Returning R1 to service. |
|
APPROVED |
2024/04/29 08:30 |
2024/05/01 12:00 |
Replace U1 PT Pullbox located in the terminal, and install new cables for new L1133 protection panels.
Unit 1 OOS to perform this work. |
|
RECEIVED |
2024/05/05 08:00 |
2024/05/05 11:00 |
Accomodate Versant Power Switching |
|
ASSESSMENT |
2024/05/16 05:00 |
2024/05/26 17:00 |
10D1 Replacement
3016-02D & G3016-4299 Maintenance |
|
RECEIVED |
2024/05/19 08:00 |
2024/05/19 11:00 |
Move Versant Power N/O back to 5-35 |
|
ASSESSMENT |
2024/05/27 05:00 |
2024/05/29 17:00 |
6D2, 3009-02D & G3009-4299 Replacement |
|
RECEIVED |
2024/05/27 08:00 |
2024/06/07 16:00 |
Station computer failover required for programming changes. |
|
ASSESSMENT |
2024/05/29 17:00 |
2024/06/05 17:00 |
6D2, 3009-02D & G3009-4299 Replacement |
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP on section of L0045. Jets need to run. PMO to working on Life Extension work up to STR105. Permit holders will be provide as we get closer. Permit Coordinator is Raja Farooq and Permit Manager is Sylvain Leblanc.
|
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP on section of L0045. Jets need to run. PMO to working on Life Extension work up to STR105. Permit holders will be provide as we get closer. Permit Coordinator is Raja Farooq and Permit Manager is Sylvain Leblanc.
|
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP on section of L0045. Jets need to run. PMO to working on Life Extension work up to STR105. Permit holders will be provide as we get closer. Permit Coordinator is Raja Farooq and Permit Manager is Sylvain Leblanc.
|
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP on section of L0045. Jets need to run. PMO to working on Life Extension work up to STR105. Permit holders will be provide as we get closer. Permit Coordinator is Raja Farooq and Permit Manager is Sylvain Leblanc.
|
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP TLM will be matching up with PMO. they will be completing replacing STR004 and STR006 |
|
RECEIVED |
2024/07/15 07:00 |
2024/07/18 18:30 |
WP TLM will be matching up with PMO. they will be completing replacing STR004 and STR006 |
|
RECEIVED |
2024/09/09 08:30 |
2024/09/09 17:00 |
Permit to remove leads 4125J002 for U5-D Replacement. |
|
RECEIVED |
2024/09/27 08:30 |
2024/09/27 17:00 |
Permit to reinstall leads 4125J002. |
|
RECEIVED |
2024/09/29 08:00 |
2024/10/08 23:00 |
Maintenance |
|
RECEIVED |
2024/10/13 08:00 |
2024/10/25 17:00 |
Maintenance |
|
ASSESSMENT |
2024/10/21 08:00 |
2024/11/10 17:30 |
Maintenance |